Changes in the West Area

  Changes in the West Area


Please have a look at:


Present working files:


The West Hall as a building was completed in 1968. Since then it has gone through three major phases:

Period Energy Characteristics
1971 till 1974 28 GeV/c (PS) Two beams, one to Omega, one for bubble chambers
1976 till 1982 200 -> 240 GeV/c (SPS) 7 beams for Omega, BEBC and other experiments
1984 till 1996 450 GeV/c (SPS) Two physics beams: H1 for Omega and H3
Four general purpose test beams: X1, X3, X5 and X7/X9


The Research Board has decided that at the end of 1996 the H1 , H3 , X1 and X3 beams should be stopped. This implies also that there will no more be ion beams to the West Area. The upstream part of the H3 beam will remain in operation to serve as a parent beam for the X5 and X7 beams.

Schematic layout of old and new West Area < click for full picture

With the material recovered from the stopped beams, the X5 and X7 beams have been upgraded to 250 GeV/c. Please click here for a PS file with the new X5 optics. The new X7 optics can be found here.

The X7 beam has also been made horizontal (in the past it sloped down towards the old BEBC center at 6 mrad). See the Beams page for more details on the special extensions to the CHORUS experiment (1997 version only - now dismantled).

The polarities of all magnets have been measured in 1998 and can be found here.

From the controls point of view the layout has been simplified according to the new synoptical diagram:


This is summarised in the diagram below:

which looks indeed much simpler than the corresponding old diagram:


The users in 1997 of the West Area beam lines are indicated in the Layout of the SPS West Experimental Area (situation for 1997).

Concerning the Layout of beam lines, the Beatch files are organised somewhat differently (for historical reasons):

With all the changes above, it is clear that the access conditions for the different beam zones has to be reconsidered. Please click here for the list of access conditions per zone.

The future injection line from the SPS into the LHC will traverse the present location of the T1 primary target. Therefore the present target will be partly dismantled and a new one has been installed about 1.5 metres to the side and 12 metres downstream. As a consequence some 600 metres of the H3 beam have been rebuilt 1.38 metres to the North. A short description of this operation is described here. Most of this work has been done in the 1999/2000 shutdown.

Modifications to the H3 beam

As stated above, most of the H3 beam will be kept operational as 'injector' to the X5 and X7 test beams.

The H3 beam in its mode of parent for the test beams was limited to 200 GeV/c due to the limited bending power of the splitters. In the upgrade project the following changes were made:

  1. The X7 splitter used to be a pair of MSSA septum magnets. These were replaced by a pair of more powerful MSSB septa. This brings the H3 top momentum to well above 250 GeV/c.
  2. The previous X5 splitter has no more reason of being. However, at this location both the X5 and X7 branches need to be deflected North towards the X5 and X7 targets, respectively. Therefore the previous MSSB septum magnet was replaced by two large aperture MBPL bending magnets.
  3. To better control the relative and absolute intensities of the beams incident on the X5 and X7 targets, two new collimators have been introduced:
  4. The part of H3 downstream of the old X5 split has been dismantled. A massive beam dump will prevent the beam to enter the West hall in case the splitter or the MBPL magnets would trip or receive a wrong current.

The West Area beams further upstream

The energy of the H3 beam affects both the X5 and X7 beams and is subject to scheduling by the SPS coordinator after discussion with the EA physicists responsible for the changes. Note that with the suppression of the T1 wobbling station, the dedicated electron mode of H3 (which has never been neded) has disappeared.
The optics drawings (Postscript files) of the H3 beam from the primary target T1 towards the secondary targets for X5 (H35) and X7(H37) are available on the Web.

The operation of the H3 beam is under the control of the SL-EA physicists with the help of the CRN operators.

The upgraded X5 beam

In fact all bends and quadrupoles in the X5 beam have been replaced or reinforced to allow higher energy particles to be transported. A synoptical diagram with beam optics and layout of the X5 beam is available for inspection. The maximum beam momentum is given by the magnetic strength and is now 250 GeV/c. This has important consequences, in particular this allows to run the X5 beam as a secondary beam as well as in tertiary mode.

The beam serves two test facilities, namely X5A (unmodified) and X5B, which has been completely rebuild. In fact the X5B area was moved upstream by several meters. It terminates with the final dump of the X5 beam.

The X5A area for general use

X5A
The X5B area shared by 
CMS and COMPASS

X5B

Downstream of this final dump an irradiation facility will be installed (sometimes called X5C). Here detectors may be tested with parasitic muons passing through the dump in the presence of background radiation produced by a radioactive source.

The Gamma Irradiation Facility

In the 1997/1998 shutdown the height of the X5 beam has been increased by about 2 cm to the standard height of 3.66 metres above the West Hall floor. This is a consequence of the changes to the X7 beam (see below). It implied a re-alignment of all elements along the beam. Upstream of the X5A test facility a XTDV mobile dump was added. Access conditions to zone PPE105 will thus be based on this XTDV, while the magnets (used so far to make the zone safe for access) can remain on. This has the advantage that the GIF irradiation facility continues to receive some muon flux during access in X5A, provided that the X5 is operated in the appropriate condition for muons.

A user guide for the upgraded X5 beam is available.

The X7 beam

In the 1997/1998 shutdown the X7 beam was upgraded to 250 GeV/c in a way similar to the X5 beam. A beatch listing is available. Note that the beam is now horizontal and therefore the beam height has been increased considerably compared to the past (more than a metre in the X7B zone). The beam can now be operated both in secondary and tertiary mode, like the X5 beam. The maximum allowed flux in secondary mode has been limited to 106 particles per burst after radiation level measurements by the RadioProtection group. As in the past, two test facilities (X7A and X7B) are available.

The new X7A area for 
general use

X7A
The X7B area used by LHCb

X7B

As a consequence of the X7 upgrade, the extension to CHORUS had to be redesigned for a final in-situ calibration. A description of the design and operation of this extension is available. The nominal trajectory of the so-called 'direct beam' through the CHORUS apparatus remained unchanged. CHORUS has now finished its calibrations and the extension X9 has therefore been dismantled.

This was once the X9 beam for CHORUS

Muons accompanying the X7 beam may traverse the BEBC and CHARM-II halls. Some explanations about the flux and spatial distributions as a function of X7 consitions are given here. For the moment this does not cause problems, but it certainly did during the running of CHORUS!

A User Guide for the X7 beam is available.

Instrumentation in X5 and X7 beams

In each of the two remaining test beams the following instrumentation is available:

In the X7 beam a CEDAR Cerenkov counter can be installed on justified request. This counter comes together with two scintillator counters (TRIG-6 and TRIG-7) and two pairs of FISCs (FIlament SCanners).

Some typical running conditions of the West Area

H3 momentum Beam composition X5 conditions X7 conditions
-120 GeV/c
Mostly pions
Some 5-10% electrons
Flexible tertiary beam
Fluxes in 102-104 range
pions, electrons or muons

Secondary pion beam with
fluxes up to 106

Flexible tertiary beam
Fluxes in 102-104 range
pions, electrons or muons

Secondary pion beam with
fluxes up to 106

-120 GeV/c
Pure electrons Tertiary e- beam
Fluxes in 102-104 range

Secondary e- beam with
fluxes up to 106

Tertiary e- beam
Fluxes in 102-104 range

Secondary e- beam with
fluxes up to 106

+250 GeV/c
85% protons
2% K+, 13% pi+
Tertiary pi+ beam
Fluxes in 102-104 range

Secondary p beam with
fluxes up to 106

Tertiary pi+ beam
Fluxes in 102-104 range

Secondary p beam with
fluxes up to 106

-250 GeV/c
Mainly pions
approx. 4% K-
Tertiary pi-, mu- beam
Fluxes in 102-104 range

Secondary pi-,K- beam with
fluxes up to 106

Tertiary pi-, mu- beam
Fluxes in 102-104 range

Secondary pi-,K- beam with
fluxes up to 106

Typical modes of operation of the West Area are described in more detail here.

And all this is now heavily exploited, as can be seen from a picture of one of the test facilility control rooms!

Some heavily used square metres of 
control room!



Comments and suggestions please to LG or Email to LG
(last update 28 February 2000)