Introduction:
Formal minutes will not be produced for this series of meetings, the
essential results are contained in the Work Package List in the SLI web
pages at:
This note is intended only to record the list of people present and to provide more detail of comments and the outstanding questions regarding the work in the BA1.
Almost all of the work taking place in BA1 during the 2000 - 2001 shutdown has been requested by SL-BT or is necessitated by SL-BT activities. A certain amount of preparation has already taken place mainly during the last shutdown.
In view of the limited storage space available and the great volume of material involved, it is a general policy of SL division that any equipment for which a use is not envisaged in the near future should be disposed of.
Il est très important de placer les demandes de tirage/démontage/modification de câbles auprès de ST-EL (M. Condemine + P. Woillet) avant la fin du mois de juin.
Planning & Co-ordination Team:
Planning J. Montès (AC/TCP), Safety to be named,
ECA4 C. Colloca(ST/TFM), ST Linkman R. Charavay(ST/DI),
BA1-BA5 C. Arimatea(SL/OP), BA3-BB3-PCR R. Giachino(SL/OP),
BA4-BB4-ECA4 G. Robin(SL/OP), BA2-BA6 X. Altuna(SL/OP),
BA7 + overall co-ordination P. Collier + A. Spinks.
Outstanding Questions: (no order of priority or chronology)
| Work Package/Activity | Responsible | Questions/Comments |
| Construction and installation of Faraday Cage base. | E. Carlier SL-BT | To be done during operations in 2000.
Is placed on top of existing false floor panels. |
| Faraday cage Electrical and Security infrastructure | To be defined | |
| Faraday cage control racks | E. Carlier SL-BT | To be done during operations in 2000. |
| Disconnection and removal of all equipement | J. Bonthond/
R. Trohler SL-BT |
Does false floor structure need to be modified? |
| Tests and Commissioning | J. Bonthond
E. Carlier R. Trohler SL-BT |
Most tests need water & power. Some may influence tunnel work. Dates to be fixed. |
| Work Package/Activity | Responsible | Questions/Comments |
| Electronics for new TT10 pick-ups. | J-P. Papis -
G. Vismara SL-BI |
Position of new pick-ups needed urgently. Racks will be reorganised. |
| Magnet interlocks | M. Gayoso SL-BT | Racks to be reorganised. New position?? |
| Existing PC upgrade | C. Mugnier SL-PO | 36 days of work. |
| Additional TT10 corrector PCs | C. Mugnier SL-PO | Beamline positions urgently required. |
| Cabling of new PCs & PUs | M. Condemine ST-EL | Definition of cables and requests for work urgently required. |
| PC tests | C. Fischer SL-PO | Services needed. Dates to be fixed. |
| Work Package/Activity | Responsible | Questions/Comments |
| Radiation control of pipework | G. Grobon TIS-RP | Kicker and dump circuits. (Others?) |
| Heat exchanger replacement | M. Nonis ST-CV | Some exchangers are bigger than before, problems with installation? |
| Computer room A.C. | M. Nonis ST-CV | No A.C. for about 5 weeks during installation. |